The reconstruction of lavatories in the Management Research building

 

The reconstruction of lavatories in the Management Research building will start from June 27th and it is estimated to be finished around late-September.
For your own safety, please stay away from the construction sites.
 
There will be power and water outages at construction areas, please utilize other lavatories at the College of Management building and the library.
 
 

The scope of works:

All lavatories in the Management Research building.


 

Progress of the construction:

Expected duration Progress of the construction Important cautions
2016.6.27 Mon.
Dismantle the original facility of lavatories in the Management Research building

(B1,1F,2F,3F)
 
1. The teacher whose laboratory is near to the Management Research building should avoid going to school during the reconstruction, in order to avoid interference by the reconstruction.
 
2. Considering the quality in class or activity, please be sure to adjust curriculum, classroom activities during the summer (July and August).
 
3. If the student whose laboratory is near to the Management Research building need to use the classroom, proposing space requirements application to Management Departure. Management Departure will assist in arranging additional space as possible.
 
4. There will be power and water outages at construction areas, please utilize other lavatories at the College of Management building and the library.
 
5. Entrance on the ground floor of lavatories in the Management Research building will be the walkway where manufacturer uses to clean up waste materials, and there will be six parking space that uses as  a temporary waste deposits area. Please DO NOT enter or exit from this entrance.
 
 
2016.6.28 Tue.
Dismantle the original facility of lavatories in the Management Research building

(4F, the corner of the library on 3F)
 
2016.6.29 Wed.
(expected to take 3-4 weeks)

Demolish lavatories in the Management Research building

(Start from B1 to 4F)

 
2016.7.15 Fri.

1.Finish Demolishing

2.Start to assemble tube and replace hydropower switch

2016.8.4 Thur.

1.Finish assembling tube

2.Finish replacing hydropower switch

1.Although the most noisy construction has been finished, it still makes some noise during the construction.

2.If your power supply is influenced, you can contact  秋萍(Qiū píng) or 示好(Shì hǎo). Will help you immediately!

 

Construtor's contacts:

For Construction and Maintenance:王瑞緹(Wáng ruì tí),Tel : 07-5252000 #2337。
For Supervision:林福原建築師事務所,林素枝(Lín sù zhī),Tel : 07-2696648。
For Contract Manufacturers:玖乘營造有限公司,涂中仁(Tú zhōng rén),Tel : 07-7679052,HP : 0930592613

Continuously updating information....Last Updated:2016.6.22 20:25

 

 